Date of commencement of the work
Глоссарий по архитектуре и конструкциям |
The date established in a notice to proceed or, in the absence of such notice, the date of the agreement or such other date as may be established therein or by the parties thereto.
|
|
Established, английский
Установленный
|
Date of agreement, английский
The date stated on the face of the agreement. if no date is stated, it may be the date on which the agreement is actually signed, if this is recorded, or it may be the date established by the award; also referred to as the contract date.
Date of substantial completion, английский
The date certified by the architect when the work, 1 or a designated portion thereof is sufficiently complete, in accordance with the contract documents, so the owner may occupy the work or designated portion thereof for the use for which it is intended.
|
|
|
|
|
|
|